In September, electricity generation amounted to outstanding 4.4GWh, exceeding energy forecasts by 19.0%. Our portfolio of powerplants under construction in Hungary increased to 18.1 MWp, out ofwhich 12.6 MWp is expected to be grid-connected before year-end2019.
Construction of the 4.6 MWp rooftop solution for ALDI StoresAustralia reached the final stage before commissioning expected inNovember 2019.